26 September 2024 | 14:20

Astana airport to change operating schedule in October

©️ Tengrinews.kz / Turar Kazangapov

Tengrinews.kz - Astana airport is set to resume 24-hour operations.

ПОДЕЛИТЬСЯ
Иконка комментария блок соц сети

Tengrinews.kz - Astana airport is set to resume 24-hour operations.

The airport's press service announced the early completion of repairs to the runway.

"Work that began on May 1, 2024, and was scheduled to last until December 24, has now been completed, and the airport will resume operations on the runway as usual starting from October 5, 2024, at 01:00 UTC," said airport representatives.

Реклама
Реклама

They also noted that while some repair work remains unfinished, it will not affect flight schedules.

"During the conducted works, the asphalt surface of the taxiway covering an area of 26,746.64 square meters was replaced, as well as the runway surface covering 53,920 square meters. The remaining minor works being carried out by the contractor will not impact the regularity of flight operations," the airport stated.

Representatives of the airport also expressed their gratitude to passengers and airlines for their understanding and patience during this period.


Показать комментарии
Читайте также
Реклама
Реклама
Join Telegram
The dollar has fallen in Kazakhstan
8 new bus routes launched in Almaty
Kassym-Jomart Tokayev arrived in Baku
Лого TengriNews мобильная Лого TengriSport мобильная Лого TengriLife мобильная